Project summary
Authorized on december 4, 2012, the Renard diamond project involves the mining of a diamond deposit. The project includes an open pit, a waste rock area, a tailings pond, a technical landfill, an ecocentre and an ore processing complex. The mine produces about 7,000 tonnes of ore daily. An airport has also been developed to transport employees of the mine and to transport diamonds. The total estimated lifetime of the mine is 20 years.
Since the official start of operations in october 2016, the project has undergone several modifications to its original certificate. The modifications authorized to the certificate of authorization can be consulted at the following link: http://www.environnement.gouv.qc.ca/evaluations/projet-sud.htm. Since the authorization of the project, requests for modification of the certificate of authorization have been issued or are being analyzed
- Application to amend the global certificate of authorization (CA) (MODCA 1) to increase the rate of extraction and ore processing at the Renard Mine. The amendment of the certificate of authorization was issued on December 20, 2019.
- Application to amend the global certificate of authorization (CA) (MODCA 2) for the environmental ans social monitoring program. The amendment of the certificate of authorization was issued on December 16, 2020.
Details on location
The Renard diamond project is located on the north shore of Lac Lagopède north of the Mistissini community. The Foxtrot property, on which the Renard diamond mine is located, is located approximately 200 km northeast of lake Mistassini, approximately 70 km north of the Monts Otish and approximately 360 km north of Chibougamau.
Documents
Amendments of the global certificate of authorization
- 2019-05-29 Les Diamants Stornoway (Canada) inc., Application to amend the global CA (MODCA 1), may 2019, 46 pages.
- 2019-10-28 Les Diamants Stornoway (Canada) inc., Application to amend the global CA (MODAC 1)-Answers to questions and comments, october 2019, 17 pages.
- 2019-12-03 Les Diamants Stornoway (Canada) inc., Application to amend the global CA (MODCA 1)-Additional information, december 2019, 5 pages (french only).
- 2019-02-01 Les Diamants Stornoway (Canada) inc., Application to amend the global CA (MODCA 2), may 2019, 298 pages.
- 2020-08-11 Les Diamants Stornoway (Canada) inc., Application to amend the global CA (MODCA 2)-Additional information, august 2020, 29 pages.
- 2021-02-15 Les Diamants Stornoway (Canada) inc., Letter-Answers to questions and comments (MODCA December 16, 2020), february 2021, 6 pages (french only).
- 2021-02-15 Les Diamants Stornoway (Canada) inc., AKUM report-Answers to questions and comments (MODCA December 16, 2020), february 2021, 126 pages (french only).
Environmental and social monitoring report
- 2019-11-21 Les Diamants Stornoway (Canada) inc., Environmental and social monitoring report 2018, november 2019, 222 pages.
- 2020-10-23 Les Diamants Stornoway (Canada) inc., Environmental and social monitoring report 2019, october 2020, 318 pages (french only).
Documents produced by COMEX
- 2019-09-03 COMEX Application to amend the global CA Questions and comments, september 2019, 3 pages (french only).
- 2019-12-06 COMEX Recommendation-MODCA, december 2019, 2 pages (french only).
- 2020-11-02 COMEX Recommendation-MODCA, november 2020, 2 pages (french only).
Table provided by MELCC
Disclaimer
Some of the information on this website may have been supplied by external sources. The Review Committee assumes no responsibility for the accuracy, timeliness or reliability of information supplied by external sources. Users wishing to rely on this information should consult directly with the appropriate source.
Global certificate of authorization issued on December 4, 2012.